Team Spy Penguins
Weekly Report – March 27, 2009
Major Deliverables
Design Document
Revision completed - Small changes
Schedule
New excel document with all of schedule and estimations in it.
Major Accomplishments
Team has started to work heavily upon release 1
Concerns/Risks
Concern that any more schedule slippage might seriously impact release as we head for the home stretch.
Status:
Some UI screens are mostly completed. XML and File subsystems are coming along well, as is the Entity subsystem. Looks like tentatively might be able to show off some stuff on Monday.